Watermain replacement construction update

This week:

  • Watermain installation continues on Grove Street and began on Gail Place.
  • Concrete sidewalk, curb and gutter, and driveway aprons getting poured on Peterson Street.
  • Spot replacement of curb and gutter getting poured on Grant Street and Spry Street.

Next week:

  • Water main installation will continue on Gail Place to Adrian Boulevard.
  • Water service lines will be installed on Grove Street in the section where watermain has been installed and passed all testing.
  • Roadway preparation for asphalt on Peterson Street to begin.
  • Roadway preparation for asphalt to begin at end of the week and into the following week for Spry Street and Grant Street.
Sidewalk concrete on Peterson                                                                                                     Curb and gutter on Peterson
20220726 Peterson sidewalk concrete - Copy  20220727 Peterson curb and gutter - Copy