Construction Update - USH 12 Resurfacing Project: Whitewater Avenue from Madison Avenue to CTH M

This is a project update for the USH 12 Resurfacing Project: Whitewater Avenue from Madison Avenue to CTH M (WisDOT Project 3575-02-73 .

Anticipated construction completion: Late August 2023

  • TRAFFIC UPDATES:
    • Week of 8/7/23 – CTH M to South 3rd Street
      • Paving operations will continue on USH 12 from CTH M to South 3rd street.  Flagging operations will be utilized for traffic through the work zone in this area.
      • USH 12 will remain open to local traffic.  Flagging operations will occur from CTH M to South 3rd Street. Expect Delays.
      • Be aware of construction equipment in the area completing paving.
    • Week of 8/14/23 – CTH M to South 3rd Street
      • Paving operations will continue on USH 12 from CTH M to South 3rd Street.  Flagging operations will be utilized for traffic through the work zone in this area.
      • USH 12 will remain open to local traffic.  Flagging operations will occur all week from CTH M to South 3rd Street. Expect Delays.
      • Be aware of construction equipment in the area completing paving.
  • USH 12 construction activities completed this week (Week of July 31)
    • Milling and Paving operations in the downtown portion, (see photos)
    • Pavement Markings in the downtown portion (See photos)
    • Milling and paving the first lift on asphalt in the S. 3rd street to CTH M section (See Photos)
  • USH 12 Construction activities anticipated next week (Week of August 7)
    • Milling and Paving operations continue from CTH M to South 3rd street.
    • Sidewalk will be poured in areas that are not complete.
    • Manholes and Inlets will be adjusted as needed prior to surface paving.
    • Topsoil placement at newly poured sidewalk locations possible late in the week.
  • Outlook for the following weeks (August 14th and beyond)
    • Paving operations will continue from CTH M to South 3rd Street to pave the surface lift of asphalt.
    • Permanent Pavement Marking operations after paving is complete.
  • All operations are weather dependent and subject to change.

3575-02-73_Downtown - Copy
3575-02-73_Milling downtown 2 - Copy