USH 12 Resurfacing Project: Whitewater Avenue from Madison Avenue to CTH M

Anticipated construction completion: August 2023

  • TRAFFIC UPDATES:
    • USH 12 will remain open to traffic.  Occasional Flagging operations will occur.
    • Be aware of construction equipment in the area completing sidewalk and curb work at each intersection.
    • Pedestrian traffic will be detoured by signs, barricades, and drums, as the NE corner of each intersection will be worked on.
    • ALL SIDEWALKS WILL REMAIN OPEN FOR THE MEMORIAL DAY HOLIDAY WEEKEND.
  • USH 12 construction activities completed this week (Week of May 22)
    • Seeding and Erosion Mat placed at newly topsoiled locations (see attached pictures)
    • ALL SIDEWALKS WILL REMAIN OPEN FOR THE MEMORIAL DAY HOLIDAY WEEKEND.
  • USH 12 Construction activities anticipated next week (Week of May 29)
    • Removal and replacement of sidewalk and curb will begin at the NE Corner of each intersection Tuesday, May 30.
    • Removal will be early in the week, with pouring concrete later in the week for each NE quadrant of each intersection.
  • Outlook for the following weeks (June 5 and beyond)
    • The NE corner of each intersection will be poured.  Asphalt patching and restoration are anticipated for the week of June 5.
    • After the NE corner, it will be the SW and lastly the SE.  Each quadrant will take approximately 2 weeks from removal to new concrete and restoration.
    • Milling and Paving operations are anticipated to begin around Mid-July.
  • All operations are weather dependent and subject to change.