Watermain replacement construction update

This week:

  • All underground utility work has been completed.
  • Grading for pavement has begun on Maple Street and Adrian Boulevard.

Next week:

  • Asphalt paving is scheduled for next Wed (9/28) through Friday (9/30) on Adrian Boulevard, Gail Place, Maple Street, Grove Street, and Spry Street.
  • Driveways that need asphalt patches will be paved during this time as well.
  • Restoration will continue throughout the project.
  • The contractor will begin to start cleaning up the project area.

****It is important that the final layer of asphalt pavement is given adequate time to cool.  Driving on it too soon or making static turns can easily damage the material.  We ask that residents use alternative parking for at least 24 hours after paving.*****